PROJECT PROGRESS
1st payment
15% upon contract signing
2nd payment
15% upon your apartments' foundation completion, with three months payment time
3rd payment
15% upon your apartments' structure completion, with three months payment time period from previous settlement
4th payment
15% upon plastering work completion, with three months payment time period from previous settlement
5th payment
15% upon chalk work completion, with three months payment time period from previous settlement
6th payment
15% upon finishing work completion, with three months payment time period from previous settlement
7th payment
15% upon title deed transfer